Graphic version of this page | Change how these pages look






Home
About Bridge Cottage
   Internal Works
      Upstairs

         
Upstairs Flooring         
         
Upstairs Framing         
         
Upstairs Plasterboard          About the Isle of Skye
About the West Highlands
Dunvegan Weather
IT Consultancy
Send a Postcard
Downloads
Building Links
Fun Links

[Image - View this page as text only] Text Only
[Image - E-mail this page]E-mail this page






Upstairs Plasterboard



Upstairs Plasterboard...
Once the framing is completed, and all the first fix jobs are done, I could then start to fit the plasterboard. As with the rest of the house, I have used 12.5mm TE plasterboard throughout, with vapour check used in the en-suite bathroom.
 
 


 

 

Here is a shot of the completed South gable wall. Most of this will be hidden by a built in wardrobe.
 
The completed wall which seperates the en-suite from the master bedroom.
 
Here I have fitted the plasterboard to the eves. I cut the board to shape, around the roof joists. I will fill the gaps and then finish off the joins between the wall and roof with some wood beading.
 
 
 
 
 

 

 

This is the final part of plasterboard to be fitted in the en-suite. As you can see most of the plumbing is in place. I have also completed the last of the electrical work in this space, such as Earth bonding.
 
The back dwarf wall in the master bedroom, ready to be taped and filled.
 

 
 
 
 
 

 

 


 

 

 
 
 
 
 

 

 


 

 

 
 
 
 
 

 

 


 

 

 
 
 
 
 

 

 


 

 

 
 
 
 
 

 

 


 

 

 
 
 
 
 

 

 


 

 

 
 
 
 
 

 

 


 

 

 
 
 
 
 

 

 


 

 

 
 
 
 
 

 

 


 

 

 





Other Useful Information