Insulation and Framing...

Below are some pictures showing the internal insulation and framing taking shape in the back extension of Bridge Cottage. The floor and walls are insulated, and frames are created for the floating floor. Finally stud work is put in against the walls, ready for plasterboard.

 

BackFloor1.jpg BackFloor2.jpg BackFloor3.jpg
This picture shows the insulation being installed, along with the frame for the floor. I'm using 50mm Kingspan insulation on the walls, and 70mm Kinspan on the floor. All the framing uses treated C16 70x45mm timber. Where there will be stud walls I have added extra bracing in the floor to carry the new wall weight. The gaps between the frames are then filled with the insulation sheets, and the joints sealed with foam and taped using aluminium foil tape. This picture shows part of the completed floor, with the frame and Kingspan insulation visible. The chipboard is only fixed at the perimeter, and where the new walls well be.
BackFloor4.jpg Plasterboard1.jpg Plasterboard2.jpg
Here is a picture of the completed floor, looking towards what will be the new bathroom and kitchen. The Kingspan currently is not held against the wall, but when the timber stud work goes up, that should help fix it in place. Getting the new floor down was momentous. But this was a major milestone - the first piece of plasterboard goes up on the ceiling. I'm using 12.5mm TE plasterboard, fixed using 30mm screws. More boards going up. We managed to get the whole ceiling covered in just one day - this took about 10 sheets, with a bit of cutting required to make them fit. This is the only drawback with renovation - nothing is square.
Plasterboard3.jpg Walls1.jpg Walls2.jpg
The completed ceiling - ready to be taped and finished. Now the wall framing can go in... Here the stud framing is going up. The studwork is fixed between the floor and ceiling - there is no connection to the outside walls. This allows the insulation to be continuous, so there shouldn't be any cold bridges. The studwork is all using 70mm x 50mm treated timber. The studs are set at 600mm centres. Putting the studs on their side creates a 50mm space between the insulation and plasterboard. This will be used to run services, such as pipe work and cables. All the joints between the insulation boards have been sealed using expanding foam, and then aluminium foil tape. This creates a vapour barrier, as required by Building Control.
Walls3.jpg Walls4.jpg Walls5.jpg
We also needed to add extra framing around the doors and windows, which the plasterboard will fix to. The front wall being framed... We are not the tidiest workers in the world! This is the back kitchen wall insulated and framed. Just noggins to go in...
Walls6.jpg BackPartitions2.jpg
I had temporarily fixed the fuse box to the porch wall. Since it was now time for this to be lined I had to move the fuse box. Best place - propped against the wall..... Here is the back porch virtually finished off. Because of space I have lined this room differently - the frame is against the wall, and the insulation is between the studs. I also needed to install a damp proof membrane above the concrete floor and part way up the walls, as this floor had been built without one.